Budget For Skate Park
|
Known and estimated costs include the following:
|
|
$7,459
|
Master plans by Wormhoudt, Inc. (completed)
|
|
$1,699
|
Soils study (completed)
|
|
6,000
|
Appraisal services (completed)
|
|
$10,000
|
Site survey (donated)
|
|
$1,500
|
Phase I site assessment (donated)
|
|
$2,000
|
City in-kind permit processing (donated)
|
|
$10,000
|
City project management (donated)
|
|
$3,050
|
Initial Study/Negative Declaration (completed)
|
|
$500
|
Printing and other costs (approximate)
|
|
$46,321
|
Design contract (ongoing)
|
|
$150,000
|
Land (purchased)
|
|
$958,599
|
Improvements (including contingency)
|
|
$1,197,127
|
Total
|
Funding sources:
|
|
$125,000
|
Open Space grant
|
|
$200,000
|
Sonoma County Partnerships for Youth grant
|
|
$73,000
|
City allocation of State 2000 Bond Act Per-Capita grant
|
|
$25,000
|
City funds from sale of land adjacent to Flynn Street
|
|
$55,000
|
City parks impact fee fund
|
|
$201,642
|
City allocation of State 2002 Bond Act Per-Capita grant
|
|
$7,912
|
City project fund donations
|
|
$23,500
|
Donated services (to date)
|
|
$9,000
|
Donated boulders
|
|
$35,000
|
West County Skate Park contribution to City
|
|
$755,054
|
Total
|
Additional funding of $442,073 is needed. However, this includes $125,035 as a contingency factor, which if not required, reduces the gap to $317,038. Also, there are desirable elements, including the manufactured climbing rock, a kiosk, a shade trellis, and a restroom, that could be added later. The estimated cost of these particular items is $64,000; if eliminated, the gap is reduced to $253,038.
|
Note:
There is potential for in-kind donation of various improvement components such as landscaping, grading, fencing, wall, and benches.
|
|
|